RHR1410

Client: Royal Hotels & Resorts s.a.l
Architect: ASAM s.a.l

Project Scope: The project unfolded through three distinct phases: Phase 1 focused on laying the groundwork with substructure concrete works to ensure the robustness and stability of the foundation. Phase 2 involved the construction of the superstructure, following the completion of the substructure, marking a crucial step in the vertical development of the blocks. Finally, Phase 3 encompassed external finishing, meticulously detailing block works, MEP (Mechanical, Electrical, Plumbing) installations, external paint application, balustrade installation, aluminum fittings, external openings, and tiling, ultimately leading to the comprehensive aesthetic and functional completion of the project.